Reduction of Air In-Leakage
and Flue Gas Bypassing in the Penthouse of Duke Power- Marshall Unit No. 4
Description of Authors:
Mr. Ron
E. Campbell Duke Power-Marshall Station Plant Manager
Mr. Thomas J. Rush Cost Effective Maintenance, Inc. President
UNIT
DESCRIPTION...
Marshall
Unit No. 4 has been one of the most efficient electric power
generating units in the USA for 25 years. This unit is a pulverized
coal fired, Combustion Engineering boiler which provides 3,500 psi
steam to a 700,000 kW tandem compound turbine. The boiler has two
stages of reheat, and the rated steam temperatures are
1,007°F/1,000°F/1,000°F. The unit heat rate has averaged 8,912
BTU/kWh for the plant is thirty year life. The boiler side elevation
is shown below in Figure No. 1.

Flue
Gas Bypassing and Ash Accumulations
Gradual
deterioration of the original penthouse roof seals resulted in flue
gas bypassing in the penthouse, and accumulations of flyash in the
penthouse. The flyash deposition in the penthouse, and flue gas
bypassing is depicted in Figure No. 2.
The
fluegas bypassing is a very small percentage of the total boiler
flue gas flow, however, over the 8000 hours or so of operation
between outages, the slow accumulation of settled flyash resulted in
ash dunes of up to five feet in depth. The bulk volume of the flyash
in the penthouse approached 100 tons. This ash remained hot, well
after shutdown of the boiler, and was removed by vacuuming. Owing to
the maze of tubing and headers in the penthouse, and considering the
specific design of this boiler with two stages of reheat steam,
there are more tube penetrations and headers in this penthouse than
most boilers. Therefore, ash removal was difficult, time consuming
and expensive.
Air
In-Leakage
Flue gas
bypassing and the consequent ash accumulations were the principal
justifications for correcting the roof seal leakage. However,
another factor is Duke Power is commitment to efficient power
generation. Air in-leakage also resulted from the roof seal
deterioration. This is depicted in Figure No. 3.

The air
in-leakage through the penthouse casing was deemed to be practically
impossible to arrest at the penthouse boundary. This is because of
the many penetrations of steam lines, vents, drains, and the
expansion and contraction of the casing for each startup and shut
down. These cycles, for this super critical boiler with 30 years of
operation, have left numerous air leak paths through the penthouse
casing. The sealing of any air in-leakage was deemed to be most
practical by sealing the tube penetrations at the roof tubes. Air
in-leakage will result in unit heat rate penalties.
These penalties to heat rate are:
1.) Dry
gas loss of heated excess air that provides no benefit to combustion
2.) I.D.
fan horsepower to remove this additional tramp air
3.) If
left to ever increasing quantities, air in-leakage will contribute
to the excess oxygen measured at the oxygen analyzers, resulting in
an oxygen starved furnace. This could lead to increased flyash
carbon loss.
Reliability, Availability and Safety
Eliminating the ash accumulations by roof sealing improvements also
reduces tube repair time in the event of a tube failure in the
penthouse, which produces lost revenue when the unit is off-line.
Electrical production from this unit is vital to the Duke System.
Additionally, there are personnel safety benefits of the maintenance
personnel not having to contend with large accumulations of flyash
that hold the heat for days.
Description of Alternatives Considered and the ISOMEMBRANEŽ System
During
the overhaul outage of the spring of 1994, the penthouse seals were
replaced with an advanced ceramic fiber sealing system. This process
was selected after evaluation of traditional weld repairs and
installation of updated metal seals. Based on past weld failures of
repairs, a new design was deemed to be required. Basically, there
were two alternatives. One was to remove the existing metal seals,
refractory and insulation, and replace with an updated hermetically
welded high crown design. The cost and outage time requirements
eliminated this approach. The other alternative was to use the
ISOMEMBRANEŽ system of sealing. This design uses advanced
ceramic fibers, cement, and anchoring systems which were developed
in Denmark. The system has been further refined and made cost
effective by the USA licensee of this system, High Temperature
Technologies, Inc. of Charlotte, North Carolina. This second method
of repair/design upgrade was selected for both technical as well as
time and cost considerations.
From a
technical standpoint, the areas to be sealed experience considerable
expansion movement. This is a result of the size, pressure, and
temperatures of this unit. The ISOMEMBRANEŽ system provides
excellent sealing, without restricting expansion movement between
the tubes. The ISOMEMBRANEŽ sealing system is shown on Figures 4, 5,
and 6 below.


The
ISOMEMBRANEŽ system requires careful surface preparation and
cleaning. Then, studs are applied to headers and tubes. ISOMEMBRANEŽ
is anchored to the proprietary studs and attachments. Use of ceramic
fiber insulation specifically designed for this service is applied.
Air and gas tight sealing is accomplished by application of high
temperature adhesives, mortars, and cement. The adhesive used is
rated to 2200°F with no volatility or other significant Haz Mat
concerns.

Scope
of Repairs
The seal
system as described on Figures 4, 5, and 6 was applied to sections
A-E, as shown on Figure No. 7.
The
installation was the result of extremely detailed coordination of
all work groups, for time expediency. Due to the vital nature of
this unit, a comprehensive coordination of all outage activities was
imperative. The schedule of implementation can be shown in Figure
No. 8.


Results
After a
year of operation, the penthouse was inspected and found to be
lightly dusted with barely sufficient accumulation to show
footprints. This is contrasted with previous five foot deep ash
dunes. The savings in maintenance repairs are estimated at $65,000
for vacuuming that was not required, and $80,000 in maintenance
personnel weld repairs. The history of repairs was such that
vacuuming and weld repair costs were predictable and, before the
ISOMEMBRANEŽ installation, always expected as recurring maintenance
costs. The heat rate improvement of reducing air in-leakage is well
known, and significant. The principal quantified savings are in
reduced maintenance costs, more expedient repairs (reduced cool down
time for repairs in the penthouse), and safety. The heat rate
improvements, though not quantified yet, are expected to be
significant. The success of the ISOMEMBRANEŽ on Unit No. 4 has
resulted in similar plans for Unit No. 3 and other units in the Duke
Power system.
The
authors wish to acknowledge the efforts of Roy Helm of Duke Power
Marshall Plant, and all of the maintenance staff at Marshall Steam
Plant. Also, Mr. Bill Turner of CEM, who was instrumental in
developing and improving the field installation techniques.
Return to Top
High Temperature Technologies, Inc.
2175 Dunavant Street
▪
Charlotte, NC
28203 ▪
704-375-2111 ▪
www.isomembrane.co